HOW TO SECURE BUILDING PERMITS

ABOUT THE SERVICE :

FOR INDIVIDUALS WHO WISH TO CONSTRUCT BUILDINGS FOR RESIDENTIAL, COMMERCIAL, INDUSTRIAL, INSTITUTIONAL OR EVEN TOWER, BILLBOARDS AND PIERS AS PRESCRIBE BY LAW UNDER THE NATIONAL BUILDING CODE (R.A 1081) SHOULDER SECURE BUILDING PERMITS AND OTHER CLEARANCES PRIOR TO CONSTRUCTION TO ENSURE PUBLIC SAFETY AND ORDER.

REQUIREMENTS:

  1. ZONING CLEARANCE (MPDC)
  2. TAX CLEARANCE (Mun. Treasurer’s office)
  3. TAX DECLARATION FOR LOT OWNER (MUN. ASSESSORS OFFICE)
  4. NOTE; IF APPLICANT IS NOT THE REGISTERED OWNER OF THE LOT WHERE THE BUILDING IS TOBE CONSTRUCTION. SUBMIT ANY OF THE FOLLOWING DOCUMENTS BELOW:
  5. LEASE CONTRACT AGREEMENT
  6. DEED OF ABSOLUTE SALE
  7. CONTRACT OF SALE
  8. NOTARIZE OENERS CONSENT
  9. WAIVER OF RIGHTS
  10. BUILDING AND STRUCTURAL PLANS & ESTIMATES SIGNED & SEALED BY A LICENSE CIVIL ENGINEER
  11. ELECTRICAL PLANS & ESTIMATES SIGNED & SEALED BY A PROFESSIONAL ELECTRICAL ENGINEER
  12. MECHANICAL PLANS & ESTIMATES SIGNED & SEALED BY A REGISTERED MECHANICAL ENGINEER
  13. SANITARY & PLUMBING PLANS AND ESTIMATES SIGNED & SEALED BY A LICENSE SANITARY ENGINEER
  14. OTHER REQUIREMENTS REQUIRED BY LAW
  15. CLEARANCE FROM AIR TRANSPORTATION OFFICE (ATO )FOR TOWERS & TALL BLDGS.
  16. ENVIRONMENTAL CLEARANCE CERTIFICATE (ECC) FROM DENR FOR INDUSTRIAL PROJECTS

FEES:

  1. ELECTRIAL PERMIT FEE                                                      PHP 25.00 MIN.
  2. MECHANICAL PERMIT FEE                                                 PHP 50.00 MIN
  3. CERTIFICATE OF FINAL ELECTRICAL INSPECTION           PHP 25.00
  4. SANITARY/ PLUMBING PERMITS                                     PHP 50.00 MIN
  5. OCCUPANCY PERMITS                                                         PHP 25.00 MIN
  6. FIRE SAFETY CLEARANCE                                                     PHP 50.00 OR ½ OF 1% OF PROJ. COST
  7. BUILDING PERMITS FEE                                                      PHP 2.50/SQM of Flr. Area

 

FOR MORE DETAILS PLEASE SEE ATTACHED SCHEDULE FOR COMPUTATIONS.

 

HOW TO AVAIL OF THE SERVICE:

STEPS AND PROCESS

DURATION

PERSON TO CONTACT

RECEIVING, ASSESMENT & REVIEW OF ALL DOCUMENTS SUBMITTED 15 MINUTES MUN. ENGR. JOVE O. RIVERA

 

COMPUTATION OF FEES & RECOMMENDING FOR PAYMENT AT THE MUN. TREASURERS OFFICE 15 MINUTES MUN ENGR.JOVE O. RIVERA
FINAL REVIEW OF PLANS AND FEES 4 MINUTES MUN. ENGR. JOVE O. RIVERA
SIGNING OF DOCUMENTS

 

3 MINUTES MUN. ENGR. JOVE O. RIVERA
RELEASING AND RECORDING

OF DOCUMENTS

 

3 MINUTES ENGR. ROLAND CABURNAY